Site screening

Desktop screening is not feasibility: reading early site scores honestly

An early site score is useful for deciding where to look harder. It is not studied capacity, not a utility commitment and not an energization date.

Published
Reading time
4 min read

Early in a project, almost everyone wants a number. How much power is near this site? How ready is it? Desktop screening can produce those numbers quickly, and used well they are valuable. Used carelessly, they become the most expensive misunderstanding in a project.

What desktop screening is for

Desktop screening means assessing a site from information that is already available: public records, filings, maps and published studies. It answers a narrow question: is this site worth a closer look?

That is a real decision. It lets a developer, an economic development office or an investor compare many candidate sites on consistent conditions and decide where to spend diligence effort.

What a screening score is not

A desktop screening score is not:

  • utility-informed feasibility — the utility has not studied the site;
  • studied capacity — no figure in it represents confirmed available megawatts;
  • an energization date — it says nothing reliable about when power could be delivered;
  • a permitting outcome — open conditions remain open.

GRIDEnable AI™ labels screening views this way on the page itself. A power screen or site readiness score from desktop screening is marked as desktop screening, and its confidence is stated as "not utility-informed".

Why the label matters

A screening score travels. It moves from an analyst's notes into an investment memo, a board slide or a conversation with a county. Each time it moves, it is tempting to drop the caveat and keep the number.

When that happens, a site that only looked promising starts to be treated as one that cleared real conditions. The cost appears later, when a utility study or a permit review contradicts the early picture, after capital has already been committed.

Keeping the confidence level attached to the number is what prevents that. So does keeping unassessed conditions visibly unassessed instead of averaging them away.

Moving from screening to evidence

The useful path is to treat a screening result as the start of diligence, not the end of it:

  1. Screen candidate sites on the same conditions, so the comparison is fair.
  2. Carry forward the sites worth a closer look, with the reasons recorded.
  3. Replace screening estimates with evidence, condition by condition, as studies, filings and utility responses arrive.
  4. Keep each condition's status tied to the record it came from.

At every step, the reader should be able to tell the difference between what has been estimated and what has been confirmed.

If you are comparing candidate sites now, request a strategic briefing and bring the shortlist.